Road To 2020 » Construction Timeline

Construction Timeline

Our Capital Improvement Project, entitled The Road to 2020, is broken down into three construction phases. Each phase was designed with the safety of our students and staff in mind.
 
Construction Phase 1: April 2018 - August 2018
Includes the following:
Richard Mann Elementary School: 
  • 5th Grade Classrooms Redesigned 
  • Main Office and Entrance Updates 
 
Gananda Middle School: 
  • Main Office and Entrance Updates (delayed until Summer 2019)
  • Masonry Restoration
 
Athletic Updates:
  • Elementary School Pool Locker Room Updates (delayed completion: December 2018)
  • Middle School Locker Room Updates (delayed completion: October 2018)
  • Lacrosse/Soccer Field Turf Application (complete, however, due to track construction, field is not open to public)
  • Track Resurfacing (delayed installation)
 
Construction Phase 2: September 2018 - December 2018
Includes the following:
Richard Mann Elementary School:
  • 2nd Grade Classrooms Redesigned
 
Construction Phase 3: January 2019 - August 2019
Includes the following:
Richard Mann Elementary School:
  • 3rd and 4th Grade Classrooms Redesigned
 
Ruben A. Cirillo High School:
  • Main Office and Entrance Updates
  • Project Lead the Way Classroom Updates
  • Masonry Restoration